What happened
On 17 November, members of a public bill committee debated the Building Safety (Remediation of Unsafe Cladding etc) Bill. According to Construction News, Liberal Democrat MP Gideon Amos put forward an amendment to require buildings undergoing cladding remediation to meet the same combustibility restrictions as new-build projects. The amendment called for external-wall assessments on existing buildings to use new-build fire safety standards.
Communities minister Florence Eshalomi set out the government’s position during the session. She said the approach to remediation was to either eliminate or permanently reduce external-wall fire risks to a tolerable level, not to require the same standards as for new construction. The committee rejected the proposed change by nine votes to two.
The committee also discussed the independence of professionals carrying out external-wall fire-risk assessments. Amos had proposed that these assessors must be independent from building owners. He warned that building owners commissioning these assessments could influence the recommendations, potentially limiting the scale of necessary remedial work. The amendment was opposed by Eshalomi, who argued that it could restrict the pool of available professionals. The committee voted against this proposal by nine votes to two.
Another proposal concerned the 10-month deadline included in the bill for completing all outstanding external wall assessments. Conservative MP Gareth Bacon called for this deadline to be delayed until there was evidence of enough qualified assessors to meet the requirement. Eshalomi responded that, in her view, the current supply of professionals was sufficient, though she acknowledged that "supply and demand are finely balanced". She urged building owners to start assessments in good time and said that genuine shortages could be considered if deadlines were missed. The committee voted to keep the original deadline, by nine votes to three.
In an afternoon session, the committee debated fines for companies that fail to cooperate with cladding safety checks. The current wording of the bill allows for penalties up to 5 per cent of the company’s qualifying worldwide revenue. Bacon proposed capping fines at a fixed level, instead of linking them to revenue. He argued that the proposed system could unfairly penalise parent companies for the actions of subsidiaries. Eshalomi clarified that the 5 per cent figure is the legal maximum and not automatic, and that each case would be judged on the facts. The committee rejected the proposal to introduce a fixed upper cap by 12 votes to three.
The background
The Building Safety (Remediation of Unsafe Cladding etc) Bill is intended to address fire-safety issues in existing buildings, especially those flagged after the Grenfell Tower fire. The current government policy is for external-wall fire risks to be identified and either removed or reduced so they fall within tolerable limits. New-build projects are subject to stricter rules, particularly on using combustible materials in external-wall systems.
As debated on 17 November, proposed amendments attempted to extend some of these stricter standards to existing buildings through mandatory external-wall assessments to the latest combustibility standards. The government has repeatedly argued that remediation should be risk-led and proportionate, asserting that the cost and disruption of making all existing buildings comply with new-build standards would be excessive.
The independence of fire-risk assessors has been a point of recurring debate. Stakeholders have raised concerns that assessors chosen by building owners may have an incentive to understate the level of remedial work required.
Availability of qualified professionals has affected the pace at which remediation programmes progress. The proposed 10-month deadline in the current draft of the bill aims to speed up the process for affected buildings. However, questions have persisted about the number of competent assessors available to take on the workload at the required pace.
Penalty levels for companies that do not support safety checks are also under scrutiny. The bill’s current approach, which links the maximum fine to a percentage of worldwide revenue, aims to discourage non-cooperation by large companies but has raised concerns about fairness and proportionality.
What people are saying
Gideon Amos, the Liberal Democrat MP behind the main amendments, said he was concerned that not applying new-build standards to remediation projects would create a "two-tier housing market." He also raised issues about the independence of fire-risk assessors, suggesting that building owners commissioning these professionals "could have an interest" in limiting the scope of remedial work they might recommend.
Florence Eshalomi, the communities minister, set out the government’s opposition to these changes. She said the government’s policy is based on eliminating or reducing risk rather than enforcing new-build standards. On independence of assessors, she warned that a requirement for independence could reduce the available pool, making it more difficult to carry out the necessary assessments. She confirmed that Homes England will audit assessments that recommend or reject remedial work.
Gareth Bacon, a Conservative MP, suggested that the 10-month deadline for completing external-wall assessments might be unfeasible given present levels of qualified assessors. Eshalomi stated that "a sufficient number of professionals are currently in place," but accepted the balance was "finely balanced." Bacon also criticised the proposed level of fines, warning that linking penalties to company revenue could unfairly affect parent companies based on the behaviour of their subsidiaries.
What happens next
The committee decisions mean that the Building Safety (Remediation of Unsafe Cladding etc) Bill will proceed without the proposed amendments to harmonise combustibility standards, enforce independence for assessors, delay assessment deadlines or introduce a fixed cap on fines.
Homes England will oversee audits of external-wall assessments, including both cases where remedial work is proposed and those where no such action is deemed necessary. Reforms to competence and regulation of fire-risk assessors and fire engineers are to be pursued through separate government initiatives.
Affected building owners and managers are advised to commission external-wall assessments promptly in order to meet the bill’s deadlines and avoid potential penalties where there are no legitimate shortages of qualified assessors. The framework for calculating fines will remain tied to a percentage of company revenue, with the government indicating that only the most serious offences would approach the 5 per cent ceiling.