What happened

The Building Safety Regulator (BSR) approved 31 Gateway 3 applications in the 12 weeks ending 1 November. This figure is more than triple the nine approvals recorded in the previous 12-week reporting period. According to Construction News, this change came after an administrative reporting error was found. The original report incorrectly stated that no Gateway 3 approvals had been issued during the period.

BSR's most recent figures show 42 Gateway 3 applications were closed. Of these, 31 resulted in approvals and 11 were found invalid. The invalid applications failed to meet initial statutory checks, such as requirements for mandatory safety documentation, according to BSR. The latest approvals included 24 internal refurbishment projects, three external remediation schemes, three transitional projects, and one relating to an NHS building.

The regulator clarified that no new-build higher-risk residential building that passed through Gateway 2 has yet reached Gateway 3. It said this means there is no current queue for newly built higher-risk buildings at the Gateway 3 approval stage.

The background

Gateway 3 is the final approval step before occupation for higher-risk residential buildings under the Building Safety Act regime in England. The process involves detailed scrutiny of completed works and safety documentation. BSR received 379 Gateway 3 applications since the regime began, up from 361 noted in the previous period. The number of live applications awaiting determination fell to 155 from 175 in the previous reporting period, suggesting some movement in the backlog.

The reporting period saw fluctuations in the number of Gateway 3 approvals. Twelve weeks before August, BSR recorded 29 Gateway 3 determinations, which indicates the approval rate is not consistently rising. The figures suggest that the volume of decisions varies between periods, rather than following a sustained trend.

BSR expanded its internal capacity by 25 staff in three months, as reported earlier by Construction News. This move was aimed at improving throughput for both refurbishment and remediation applications.

The numbers

The median Gateway 3 approval time increased slightly, from 20 weeks in the last period to 21 weeks in the most recent one. BSR said that, despite the longer timescale, it expects the volume of determinations to pick up as more active refurbishment projects finish onsite and staffing increases begin to show an effect. Currently, 155 live applications are in the system, down 20 from the previous period.

Among the Gateway 3 approvals, 24 relate to internal refurbishment, a common type given the occupation dependency and the likelihood that these involve buildings that remain at least partly occupied during works. Three approvals concerned external remediation, and three applied to transitional projects, while one involved an NHS scheme.

At Gateway 2 — for new-build and conversion applications — BSR approved 40 of 42 applications in the latest period, covering 9,453 homes. The median approval time at this stage fell, dropping from 23 weeks in the previous report to 20 weeks.

What people are saying

A BSR spokesperson told Construction News the regulator expects determination volumes to rise steadily as more refurbishment projects finish and the organisation completes onboarding of new internal staff. The spokesperson said BSR has prioritised Gateway 3 applications where occupation of a building depends on the final approval. It also cited efforts to improve capacity for assessment as further recruitment and internal expansion continue.

BSR said 11 of the Gateway 3 applications closed in the latest period were invalidated due to missing or incomplete statutory safety documentation. This means their processing stopped before a full technical assessment took place.

What happens next

BSR expects an increase in Gateway 3 submissions as more projects approved at Gateway 2 complete construction and move to the final approval step. The authority is still onboarding new staff to address the growing volume of applications, particularly for refurbishment and remediation schemes.

BSR continues to monitor submission compliance and regularly updates its reporting following review and administrative correction. According to the regulator, the absence of new-build higher-risk schemes reaching Gateway 3 means there is currently no build-up of new-build projects awaiting final approval. The focus remains on processing refurbishment and remediation projects, many of which involve ongoing occupation of existing buildings.

BSR will track future trends in both overall applications and decision times as more projects move through the construction pipeline and additional staffing comes online.