What happened
Cherwell District Council reported that a structural inspection of a building under construction on Cherwell Street identified a significant risk of further collapse. The inspection follows an incident in October when part of the scaffolding and building fell, injuring two workers. In response to the risk, the council closed Cherwell Street to traffic on the night of 17 November. The council also advised the neighbouring garage to close to the public and recommended that residents of adjacent flats remove their vehicles from the section of the car park nearest to the site.
Oxfordshire County Council said that traffic resumed on Cherwell Road the following day, but part of the normal road space remains closed because of its proximity to the damaged scaffolding. The Health and Safety Executive (HSE) initiated an investigation into the incident at the construction site. The contractors involved in the project have not been identified in reports so far.
The background
The site was previously occupied by a car sales business. It is being redeveloped into a mixed-use scheme, including 19 apartments and commercial units. According to the original planning application, the project received consent in November 2019. The precise cause of the partial collapse has not been disclosed, but immediate risks to the structure were identified by a structural engineer during a post-incident inspection.
Cherwell District Council has stated it is working closely with the building developer, structural engineers, Oxfordshire County Council, and other agencies to secure the site. The council said it is taking urgent action to protect public safety and that it will continue monitoring the situation. Authorities said further enforcement action would be taken if required to ensure public safety and site security.
What people are saying
A spokesperson for Cherwell District Council said urgent safeguards were put in place after the inspection, including closing the road, contacting the neighbouring garage, and advising residents about car park restrictions. The council is determined to make the area safe as quickly as possible.
A representative from the Health and Safety Executive confirmed that it launched an inquiry after the October collapse. The HSE noted that the road closure is a matter for the local council but emphasised they are supporting the council and working with contractors at the site. The HSE spokesperson acknowledged the difficulties the situation has caused for both residents and businesses in the area.
What happens next
Cherwell District Council will continue to monitor the development closely and may pursue enforcement action if additional hazards to the public or site security arise. Repairs or further stabilisation work on the structure are likely to proceed alongside the investigation. Part of the road on Cherwell Street will stay closed until it is deemed safe for full reopening.
The Health and Safety Executive's investigation is still underway, and they are collaborating with local authorities and contractors to make the site secure. The council also plans to keep local residents and business owners informed about developments affecting access, safety measures, and any further road or site restrictions. No timeline has been given for the completion of remediation-found) work or for when full access to the road or neighbouring properties will be restored.
The developer for the project has not been publicly identified in recent council statements. The names and details of the contractors working on the scheme have also not been released at this stage. More information is expected to be provided as the investigation progresses and as risk mitigation measures are put in place.