What happened
Kier has obtained planning approval to build two residential towers of 30 and 17 storeys in central Birmingham. The buildings are planned for the junction of Holliday Street and Bridge Street, near Gas Street Basin and Centenary Square, according to Construction Enquirer.
TP Bennett designed the towers, which will deliver more than 500 apartments. The project also includes ground-floor commercial spaces and communal facilities. These will provide lounges, gyms and workspaces for residents.
The development will add landscaped public areas and new pedestrian routes. These links will connect the site to the wider 1.2 million square foot Arena Central scheme. Birmingham City Council’s planning committee approved the project despite opposition from some neighbouring interests.
The background
The taller of the two buildings will become a prominent feature in Birmingham's skyline. Construction Enquirer reports it will be taller than the nearby Alpha Tower. The site is located at a gateway to Arena Central, an ongoing large-scale mixed-use development. Arena Central has already brought commercial buildings including the HSBC UK headquarters. The masterplan covers over 1.2 million square feet and is reshaping a prominent area that once housed Central Television studios and the Birmingham Register Office.
The TP Bennett-designed scheme provides a mix of one, two and three-bedroom apartments. Ground floor space is set aside for retail and commercial use, while the upper levels will contain private and shared amenities. Public landscaping and walkways form part of the broader Arena Central regeneration, linking new and existing spaces.
What people are saying
The planning process drew objections from HM Revenue and Customs, which has offices next door at 3 Arena Central. According to Construction Enquirer, HMRC raised concerns over privacy and potential overlooking of their sensitive office spaces. In addition, Historic England and the Canal & River Trust raised questions. They cited the towers’ possible effect on nearby heritage assets and the canalside setting.
Council planning officers reviewed the scheme and acknowledged the issues raised. Their conclusion, as reported, was that the "benefits of delivering more than 500 homes and completing the regeneration site outweigh the potential harm" to neighbouring sites or heritage concerns. The council’s decision enables the next phase of Arena Central’s development to proceed.
What happens next
Following the grant of planning approval, Kier will move toward the next project stages. This typically involves detailing construction plans, pre-construction surveys and issuing contractor appointments. The council’s approval indicates the planning risks have been cleared.
Construction Enquirer notes that Arena Central has already delivered key commercial developments, including HSBC UK’s headquarters. The two new residential towers will help meet local housing supply targets while increasing the area’s commercial activity. As the site is close to completed phases, coordination with existing infrastructure and residents is likely to form part of the project delivery.