What happened
Speller Metcalfe will deliver phases one and two of the Tipton Regeneration Scheme in the Black Country after Sandwell Metropolitan Borough Council approved its appointment. The scheme was left unfinished following the collapse of Torsion Construction. The council's Cabinet agreed to the appointment after conducting a competitive evaluation through the Constructing West Midlands (CWM) framework, according to council leader Ray Nock.
Torsion Construction was previously awarded a £13.2m contract to build 55 affordable homes as part of the project. The contractor entered administration in summer 2024, leaving a partially constructed site, as set out in a report to the council. The council stated that appointing a new contractor was necessary to progress the works and minimise delays.
The contract awarded to Speller Metcalfe covers the remaining work for both phases of the affordable housing scheme. The precise value of the new contract has not yet been finalised, but the council warned that it could be higher than the original Torsion deal due to current cost estimates.
The background
Torsion Construction’s £13.2m job formed part of the wider Tipton Regeneration Scheme. The firm collapsed into administration during summer 2024, halting all site activity. Sandwell Council described the site as partially completed and warned of risks to the delivery of the approved housing scheme if a replacement contractor was not sourced promptly.
Ray Nock said Speller Metcalfe’s appointment followed a full evaluation via the Constructing West Midlands framework. The CWM framework is a regional procurement system designed to allow local authorities to appoint contractors efficiently for major construction projects.
A council report listed the primary reason for using the CWM framework as the need to secure a compliant and established procurement route. According to the same report, this approach enables the council to minimise delays, reduce the risk of grant clawback and support delivery within the agreed timescales. The report stated that failure to find a replacement would delay regeneration objectives and increase the risk of missing grant funding conditions.
The council has not confirmed how much over budget the project may run. Officers are considering several funding options, including the Housing Revenue Account, external grants, and existing regeneration capital resources. The report to Cabinet indicated that further funding would be required to complete the scheme, but did not detail specific figures.
What people are saying
Council leader Ray Nock said that Speller Metcalfe had a record of delivering projects for Sandwell Council and experience in taking over sites where a previous contractor had entered administration. Nock stated that appointing Speller Metcalfe was the practical route to delivering the scheme and fulfilling the council’s regeneration aims. He emphasised the importance of minimising delay, securing a replacement through an approved framework, and protecting grant funding.
The Cabinet report submitted to councillors said the use of the CWM framework "provides the most effective means of progressing the project within the timescales required." It argued that sourcing a new contractor was necessary to avoid leaving the site partially completed and to ensure the council could deliver the housing scheme as planned.
In the wider context, Construction News also reported on recent appointments following previous Torsion Construction collapses. In October 2024, a contractor was soon to be appointed on an ex-Torsion luxury residential scheme in north Leeds. In September 2024, AC1 was confirmed as contractor for completion of a £26m residential tower previously started by Torsion Construction in north London.
What happens next
Speller Metcalfe will begin work on the unfinished phases on site to complete the 55-home affordable housing scheme. The council is continuing to evaluate the exact additional funding required and is weighing several options to meet possible budget overruns. Completion dates and details of changes or remediation for previous work carried out by Torsion Construction have not been given.
The council is focused on meeting grant funding conditions and delivery deadlines to avoid the risk of clawback. According to the Cabinet report, a compliant procurement and timely appointment were needed to protect all external funding arrangements and keep delivery of the homes on track.
Cabinet papers indicate that without a replacement, delivery of the housing scheme would be severely delayed, undermining regeneration targets for the area. The precise handover arrangements between the administrators of Torsion Construction and Speller Metcalfe have not been detailed in published documents. Further council updates are expected as the project progresses.