What happened
M B Plant, trading as 123 Fire, has successfully opposed an application for immediate judgment or to have parts of its defence struck out in an ongoing legal dispute over leaking sprinkler pipes at James House in York, according to Construction News.
John Wright Electrical & Mechanical Services (JWE), which carried out mechanical and electrical works on the scheme converting James House into offices and flats, is seeking to recover costs involved in remediating defective fire suppression systems. The High Court ruling, delivered by Judge Kelly on 20 November, declined to resolve ultimate responsibility for the defects, instead focusing on whether alleged admissions by M B Plant meant parts of its defence should be struck out or summary judgment granted to JWE.
The background
The City of York Council appointed Robertson Construction Group as main contractor in the conversion of James House to office and residential use for homeless and vulnerable people. Robertson brought JWE on board as mechanical and electrical subcontractor. JWE then subcontracted the design and installation of a water misting fire suppression system to Premier Mist UK, and employed M B Plant for fire-stopping works.
Original design drawings required the use of BlazeMaster pipework, but Flameguard pipework was installed as a substitute. M B Plant was not notified of the change, according to the court documents. For sealant, M B Plant applied Intumastic rather than the graphite mastic it initially specified at tender.
Leaks in the sprinkler pipework were first identified in October 2022. A Premier Mist UK report linked the leaks to degradation of the pipes, which the report attributed to chemical incompatibility between the pipe material and the sealant. JWE commissioned a separate report, which similarly concluded that the materials were incompatible. As a result, JWE deemed the building unfit for habitation due to concerns about the effectiveness of the fire suppression system.
M B Plant declined an offer to participate in the remedial works, which were carried out from November 2023 to February 2024. The value of the costs JWE is seeking to recover remains undisclosed.
What people are saying
M B Plant maintained before the court that it had verified the compatibility of its Intumastic sealant with the originally specified BlazeMaster pipework. The company argued that the issue only arose because Flameguard pipework was substituted without its knowledge. It also held that responsibility for incompatibility should sit elsewhere if the installed materials differed from those it had checked.
JWE argued that M B Plant had made admissions during pre-action correspondence, conceding a broader liability for the defects than it later claimed in its formal defence. JWE claimed these statements showed inconsistency in M B Plant's position.
Judge Kelly rejected JWE's argument, stating that reading the correspondence out of context was misleading regarding M B Plant's position. She found that M B Plant accepted a responsibility to exercise reasonable skill and care but did not accept accountability as broadly as JWE contended. The judge noted there were no clear admissions of breach of duty or causal responsibility for the defects. She also said that even if admissions had been made, striking out parts of the defence would be disproportionate.
What happens next
Responsibility for the cost of remedial works at James House remains unresolved. As the parties proceed to trial, the court will have to decide where liability lies for the incompatibility and failure of the fire suppression system. Neither the court nor the published judgment gave details of the sums involved.
The arguments around specification changes, notification of material substitutions, and the scope of subcontractor responsibility are likely to be further examined. The case will continue through legal process unless settled prior to trial.